Thursday, September 16, 2010

"Give my team an hour, and we're unbeatable!"


So a lot has happened since I last "blogged."


I don't work at the landfill anymore (at least officially)

I graduated with a Bachelor's of Science in Environmental Engineering at Utah State University

I worked the summer doing instrumentation on the I-15 Core project for Kleinfelder. I installed and read instruments like these to monitor settling and such.

I Started back at USU to do a master's degree and what else...


...oh yeah, I got married! :)

Tuesday, December 22, 2009

All in a Haze



I'm back at the landfill after another successful semester (4 A's, 2 B's, one more semester left). I'll only be here for a couple weeks during the Christmas break, but there's always something to do. Right now I'm updating the AsBuilt schematics for the O&M Building and the Scalehouse.




Monday, August 10, 2009

FIRE!!!!

Along with the new culvert job, there was a big mess made last week when the landfill caught on fire. Last Thursday was really windy across the valley and there was a lot of lightning. There were big fires in Skull Valley, out by Salt Lake International Airport, and out by us. The fire started sometime around 4:30 on Kennicott's (RIO TINTO) property then blew across the highway onto our property. It started on our side by the water tower and headed north along the berm that separates our main building and the highway. Luckily we have really competent operators that fought the fire with the water truck and dozer, preventing the building from catching on fire, until the firefighters could show up and take over. The firefighters showed up and put the fire out. We had around ten acres or so get scorched and a couple power poles to Granger get toasted and need to be replaced. On the plus? side, the landfill now smells like smoked hickory which is nice....unless you have an office...because then it just burns your eyes.









Ironically, all the weed pulling we did a few posts back was really worthless since it would've gone up in flames anyway.

When the boss is gone...

Last week my boss, my supervisor, and Esther were gone...so I made a mess! It was fun. Craig, the operations manager, asked me about doing another riprap job but it ended up into a culvert replacement. The culvert that goes under the road and into the overflow pond was undersized (6" diameter) and was buried under at least 24" of sediment. We decided to replace it with 2-12" diameter HDPE pipes that had been left over from our LFG piping job. I got to be the foreman in charge of a backhoe, scraper, and dozer. We dug out the old culvert, replaced it with the new pipes, dug out the inlet side and the overflow pond, buried the new pipe, and re-graded the road.
An overview before we started

Laying the new pipe
Digging out the inlet side
View of new culvert and dug out inlet side
Grading and repairing road
Digging out the overflow pond

Thursday, July 30, 2009

Landfill Pioneer

I've been thinking of doing percolation tests here at the landfill for a long time now. We've been thinking of installing a drainfield in the active cell and running condensate or leachate into it to help with gas production. In order to properly design a drainfield, you need to know the percolation rate of the soil where the drainfield is going to be installed. I couldn't find anywhere where someone had done a perc test in garbage, so I think I'm the first one to ever do one...at least that's what I'm telling myself. First I had to dig the holes.



Esther and I started digging the holes, but only got 16 of the 36 inches deep after 1 1/2 hours of digging with a shovel, post hole digger, and breaker bar. That's when I decided to use the backhoe. It made the holes bigger than I wanted, but was a lot faster and easier, especially since I did three holes. Garbage sucks to dig through!
We then had to keep water in the holes for a couple of hours to saturate the soil. This proved to be difficult. I used our water truck to fill the holes with water, since that would be the most efficient, especially for the size of the hole. I started spraying, hoping that the hole would fill up quickly but that's not what happened. Even with the good compaction we are getting, there is still a large amount of pore space in garbage that water just moves right through it. After five minutes of filling with the fire hose from the water truck, the hole only filled in six inches. I decided I wasn't going to be able to fill the holes as much as I wanted. I filled the hole to about 10 inches and moved on to the next hole. I filled the next hole, again only to about ten inches, and checked on the first hole. The water was already gone. I looked at the second hole that I had just barely filled to ten inches and the water in that one was already gone. I had a feeling it was going to be quite difficult to keep the water level up for four hours.

The next day I went back out to run the actual perc test. Now in a perc test, after the soil (or in this case, the garbage) has been saturated you fill the hole with water and measure the time it takes for the water to drop i.e. minutes per inch. So I filled the hole with water and before I could fill the next hole, the water level, as it had before, dropped completely. I concluded that garbage has a really low (or in other words, a really fast) perc rate.

I decided to switch gears and try running a perc test in the native soil. I dug two holes in the native soil and started saturating them.

I'm pretty sure these tests are going to be much different. I saturated the holes but didn't have time to run the tests the next day, (I'll have to start over) but came back four days later to see that one of the holes still had water in it. I think this soil is a little less permeable than the garbage.


Wednesday, July 15, 2009

Rocky Mountain Recyclers

Besides installing a new toilet, I had the opportunity to attend the open house for Rocky Mountain Recyclers yesterday. They expanded their existing building and added new state of the art sorting machines.
First the garbage is dropped on the "Tipping Face," then scooped by the loader into the machine



















It is then pre-sorted by hand




















It goes through a series of conveyors that sort
















This optical sorter scans the product and uses discharges of air to pull out #1 and #2 plastic


This machines launches cans off the belt so they can be bailed into huge cubes




















There's a magnet to pull out ferrous metals








Everything is then bailed and shipped out by rail car or semi-trailer


Other Jobs Not Specified


When I agreed to take this internship, I was told that it would involve engineering jobs and projects, and "other jobs not specified." I had one of those this week. We purchased a new toilet that is more wheelchair friendly, and I was chosen to take the old one out and replace it with the new one. I thought it would be entertaining to include it in my blog.


Here I am installing it



My boss performing the ceremonial "First Flush"





And beautiful finished product




Now here at the landfill, we're all about recycling and reusing, so when one of the supervisors mentioned that he needed a new chair I jumped on the opportunity to show my care for the environment.

Reduce, Reuse, and Recycle!!